Assembly Routing Problem (ARP)
CIRRELT, GERAD & HEC Montreal, QC Canada, 2015

ARP test instance number	215
ARP instance class number	2

No of suppliers/components	14
No of periods	6
No of truks	1
Truck capacity	2880
Production capacity/period	156
Unit production cost	44
Production setup cost	2200

Depot	X	Y	I_00^0	L_0	L_0^0	h_0^0	d_t
0	436	998	19	15560	37	44	13

Sup	X	Y	L_i	b_i	I_i0	h_i	I_i0^0	h_i^0	s_it
1	891	596	26	5	13	3	0	4	13
2	768	146	54	5	36	4	0	4	18
3	858	633	96	6	80	2	0	3	16
4	12	256	90	3	75	3	0	4	15
5	165	108	18	3	12	1	11	1	6
6	672	15	66	5	44	1	0	1	22
7	492	239	60	1	48	2	0	2	12
8	776	382	27	6	18	2	0	3	9
9	741	946	85	3	68	3	0	3	17
10	772	16	55	7	44	4	0	6	11
11	453	141	80	1	64	3	0	5	16
12	124	508	25	8	20	1	9	1	5
13	210	132	90	1	75	1	0	1	15
14	798	710	57	9	38	2	0	3	19