Assembly Routing Problem (ARP)
CIRRELT, GERAD & HEC Montreal, QC Canada, 2015

ARP test instance number	392
ARP instance class number	4

No of suppliers/components	14
No of periods	6
No of truks	1
Truck capacity	3220
Production capacity/period	168
Unit production cost	165
Production setup cost	8250

Depot	X	Y	I_00^0	L_0	L_0^0	h_0^0	d_t
0	574	399	12	17978	44	165	14

Sup	X	Y	L_i	b_i	I_i0	h_i	I_i0^0	h_i^0	s_it
1	356	638	48	5	32	0	0	8	16
2	307	258	30	5	24	0	12	7	6
3	143	253	25	8	20	0	22	6	5
4	604	302	27	5	18	0	0	5	9
5	66	243	126	5	105	0	0	5	21
6	68	606	48	9	40	0	0	9	8
7	996	495	120	3	100	0	0	5	20
8	910	952	44	9	22	0	0	7	22
9	496	778	84	7	70	0	0	8	14
10	109	406	38	1	19	0	0	9	19
11	781	56	26	3	13	0	0	6	13
12	249	803	85	5	68	0	0	9	17
13	684	852	78	4	65	0	0	7	13
14	319	284	84	1	70	0	0	8	14