Assembly Routing Problem (ARP)
CIRRELT, GERAD & HEC Montreal, QC Canada, 2015

ARP test instance number	89
ARP instance class number	1

No of suppliers/components	14
No of periods	6
No of truks	1
Truck capacity	1680
Production capacity/period	180
Unit production cost	269
Production setup cost	13450

Depot	X	Y	I_00^0	L_0	L_0^0	h_0^0	d_t
0	148	799	13	17340	44	269	15

Sup	X	Y	L_i	b_i	I_i0	h_i	I_i0^0	h_i^0	s_it
1	713	276	48	1	40	8	0	15	8
2	614	517	14	2	7	6	28	11	7
3	286	506	18	2	12	9	29	10	6
4	209	605	65	4	52	6	0	8	13
5	132	486	108	2	90	9	0	11	18
6	137	212	55	4	44	6	0	8	11
7	993	991	75	2	60	8	0	15	15
8	821	905	40	7	20	8	0	14	20
9	993	557	115	4	92	8	0	13	23
10	218	813	28	1	14	8	0	8	14
11	562	113	44	8	22	6	0	11	22
12	499	606	27	5	18	7	5	10	9
13	368	705	126	5	105	6	0	8	21
14	639	568	144	7	120	6	0	6	24