Assembly Routing Problem (ARP)
CIRRELT, GERAD & HEC Montreal, QC Canada, 2015

ARP test instance number	290
ARP instance class number	3

No of suppliers/components	50
No of periods	6
No of truks	50
Truck capacity	2880
Production capacity/period	156
Unit production cost	264
Production setup cost	13200

Depot	X	Y	I_00^0	L_0	L_0^0	h_0^0	d_t
0	1090	2495	5	58186	49	264	13

Sup	X	Y	L_i	b_i	I_i0	h_i	I_i0^0	h_i^0	s_it
1	2225	1490	26	7	13	3	0	5	13
2	1920	365	54	8	36	4	0	4	18
3	2145	1580	96	1	80	2	0	3	16
4	30	640	90	7	75	3	0	4	15
5	410	270	18	9	12	1	25	1	6
6	1680	35	66	1	44	1	0	1	22
7	1230	595	60	6	48	2	0	3	12
8	1940	955	27	5	18	2	1	3	9
9	1850	2365	85	6	68	3	0	5	17
10	1930	40	55	2	44	4	0	7	11
11	1130	350	80	6	64	3	0	5	16
12	310	1270	25	3	20	1	23	1	5
13	525	330	90	3	75	1	0	1	15
14	1995	1775	57	6	38	2	0	2	19
15	155	1840	18	1	12	3	25	4	6
16	1430	125	39	8	26	2	0	3	13
17	1630	1635	85	2	68	1	0	1	17
18	1135	1070	33	8	22	4	0	4	11
19	930	1150	55	4	44	2	0	3	11
20	35	2025	96	6	80	1	0	1	16
21	175	885	39	7	26	2	0	3	13
22	335	2065	55	5	44	4	0	5	11
23	1370	660	65	5	52	3	0	3	13
24	1720	1685	72	1	48	1	0	1	24
25	495	2285	80	9	64	3	0	3	16
26	2260	690	33	9	22	2	0	3	11
27	1465	1865	84	1	70	2	0	2	14
28	1085	650	114	8	95	1	0	1	19
29	650	110	36	2	18	3	0	4	18
30	1875	1645	50	7	40	3	0	3	10
31	1015	645	46	9	23	4	0	6	23
32	2320	190	18	9	12	2	25	2	6
33	2345	990	27	3	18	1	1	1	9
34	1245	1360	32	3	16	3	0	4	16
35	1840	625	80	4	64	3	0	5	16
36	2335	760	65	1	52	1	0	1	13
37	565	890	48	7	40	4	0	6	8
38	2375	1320	33	4	22	4	0	4	11
39	1940	0	10	5	5	4	38	5	5
40	1950	215	105	3	84	1	0	1	21
41	1850	1945	36	6	30	4	7	4	6
42	2290	775	120	1	96	3	0	5	24
43	105	1890	120	4	100	4	0	7	20
44	1770	405	16	1	8	2	17	3	8
45	2060	490	12	3	6	2	31	3	6
46	650	305	10	7	5	1	38	1	5
47	1105	1110	15	3	10	2	33	3	5
48	800	1275	44	4	22	2	0	3	22
49	2010	2335	85	4	68	1	0	1	17
50	1575	1930	48	3	32	4	0	7	16