Assembly Routing Problem - CIRRELT, GERAD & HEC Montreal, QC Canada
set	ins_id	class	trans_cost	n	l	m	Q	C	u	f	d_t	tot_time	sln_val	
50	48	3	2	50	6	50	3220	156	1630	163000	13	313.87	796118	
p_t	x_ijt	q_it	and_so_on
0.01	-1
2	0	0	12	52	39	52	49	41	15	28	1	110	2	34	44	22	4	33	50	24	30	48	35	15	7	85	34	23	10	85	36	17	0	0	18	36	43	14	31	72	5	28	23	5	32	17	20	21	16	72	22	24	33	55	9	8	21	70	48	33	47	28	11	28	27	36	19	28	8	28	0	0	24	32	42	120	29	28	0	0	46	5	3	15	25	19	45	63	28	68	26	16	13	28	41	51	17	80	14	36	37	55	6	95	40	28	38	13	0	0	-1
26.01	0	0	38	26	46	19	3	15	25	19	45	21	26	32	9	20	16	18	20	7	32	34	23	19	43	28	50	24	44	22	30	12	35	15	34	92	36	34	0	0	-1
0.01	0	0	29	37	8	27	24	48	3	15	25	19	19	26	27	54	11	13	47	17	41	34	14	18	35	15	50	24	44	22	2	51	15	26	0	0	-1
13.01	0	0	38	13	46	13	40	26	3	15	25	19	28	17	26	32	13	26	48	11	9	13	22	13	20	14	32	17	18	36	23	13	5	26	31	48	43	14	4	22	44	22	50	24	35	30	34	0	36	34	0	0	-1
13.01	0	0	38	13	46	13	3	15	25	19	45	21	11	13	47	9	48	11	9	13	22	13	20	7	32	17	23	13	43	14	50	24	44	22	49	13	39	13	12	13	0	0	-1