Production Routing Problem - Instances From Archettie et al. (2011)
Best Found Solution - CIRRELT, GERAD & HEC Montreal, QC Canada
set	ins_id	class	trans_cost	n	l	m	Q	C	u	f	tot_time	sln_val	
100	8	3	2	100	6	100	252	UL	30	3000	1225.28	167143	
p_t	x_ijt	q_it	and_so_on
0.01	-1
970.01	0	0	33	12	44	12	36	19	81	11	69	15	68	10	73	12	78	6	5	23	19	16	80	14	34	14	92	18	8	16	63	48	0	0	64	0	23	30	60	6	98	18	42	23	24	12	79	18	48	18	51	15	99	38	45	21	77	23	0	0	91	0	18	12	66	11	85	22	21	28	15	22	17	26	25	0	55	10	22	44	61	24	10	36	65	17	0	0	94	18	31	5	6	10	74	14	76	12	49	22	100	48	72	9	58	19	35	14	97	7	32	32	93	18	89	5	87	0	43	0	71	10	3	7	0	0	-1
0.01	-1
1784.01	0	0	63	48	0	0	60	12	98	36	42	46	24	18	79	27	48	36	51	30	11	8	99	38	20	0	0	0	77	46	64	11	4	6	45	42	23	30	10	36	59	10	2	13	65	34	27	24	0	0	89	10	84	6	35	28	70	20	58	38	72	18	100	48	49	44	21	28	14	8	0	0	62	20	61	24	16	8	22	44	55	20	25	0	17	39	15	44	85	22	66	22	0	0	31	10	6	15	74	14	7	22	76	24	93	36	32	32	97	14	41	12	88	5	19	32	80	28	26	5	43	0	0	0	86	14	18	24	94	36	92	36	8	32	71	20	69	30	36	38	33	12	0	0	3	14	34	21	29	24	12	9	5	46	78	12	38	5	90	20	73	12	68	10	46	21	52	23	81	22	44	12	0	0	-1
0.01	-1
1310.01	0	0	86	14	8	16	92	18	30	17	26	5	80	14	19	16	88	5	41	12	97	7	32	16	93	18	76	12	74	7	31	5	83	20	57	18	56	13	94	18	0	0	3	7	47	12	69	15	29	24	12	9	28	8	78	6	5	23	37	9	38	5	82	21	73	6	1	21	95	24	68	5	46	21	52	23	81	11	0	0	33	6	44	6	36	19	63	24	0	0	77	23	64	11	4	6	23	15	45	21	20	11	60	6	99	19	11	8	51	15	48	18	98	18	42	23	50	6	59	10	65	17	27	24	0	0	91	7	9	11	39	17	66	11	85	11	13	14	15	22	25	19	55	10	96	21	22	22	16	8	61	12	62	20	10	18	75	15	2	13	0	0	18	12	14	8	21	14	49	22	100	24	72	9	54	20	58	19	67	17	70	20	53	20	35	14	40	7	84	6	89	5	87	9	43	16	71	10	0	0	-1