An Improved Branch-and-Bound Algorithm for the One-Machine Scheduling Problem with Delayed Precedence Constraints

Published Online:https://doi.org/10.1287/ijoc.2020.0988

In this paper, we discuss the one-machine scheduling problem with release and delivery times with the minimum makespan objective. Both heuristics and branch-and-bound algorithms have been formulated for the problem. One such branch-and-bound algorithm solves the problem and a variation that requires a delay between the completion of one job and the start of another (delayed precedence constraints). This paper analyzes key components of this branch-and-bound algorithm and proposes an improved heuristic to be used in conjunction with a different search strategy. Computational experiments demonstrate that the modifications lead to substantial improvements in running time and number of iterations on the one-machine problem instances both with and without delayed precedence constraints.

INFORMS site uses cookies to store information on your computer. Some are essential to make our site work; Others help us improve the user experience. By using this site, you consent to the placement of these cookies. Please read our Privacy Statement to learn more.