High Technology Manufacturing in Low Technology Plants

Published Online:https://doi.org/10.1287/inte.23.6.25

We performed a two-year case study on the ramp-up of a large flexible assembly system in a Midwestern automotive components plant. The new system was designed to be a creative replication of technology already in operation in the technology supplier's firm and was purchased under a broad corporate alliance agreement as well as a detailed adoption contract. Although the project met its installation schedule, production targets, and direct labor cost savings objectives, the installation of this innovative, partially-tended assembly system raised several issues and questions regarding the optimal part mix schedule, quality standards, and maintenance schedules. We hypothesize that a curvilinear relationship exists between supplier-user satisfaction and flexibility outcomes. Moderate levels of satisfaction appear to maximize the ratio of part families per hour change-over capability of a new flexible system.

INFORMS site uses cookies to store information on your computer. Some are essential to make our site work; Others help us improve the user experience. By using this site, you consent to the placement of these cookies. Please read our Privacy Statement to learn more.