A Branch-and-Bound Procedure for the Generalized Resource-Constrained Project Scheduling Problem

Published Online:https://doi.org/10.1287/opre.45.2.201

In this paper a branch-and-bound procedure is described for scheduling project activities subject to precedence diagramming type of precedence relations, ready times, due dates, and variable multiple resource availability constraints, where the objective is to minimize project duration. The procedure is based on a depth-first solution strategy in which nodes in the solution tree represent resource and precedence feasible partial schedules. Branches emanating from a parent node correspond to exhaustive and minimal combinations of activities, the delay of which resolves resource conflicts at each parent node. A precedence based lower bound and several dominance rules are introduced in order to restrict the growth of the solutions tree. The procedure has been programmed in the C language. Extensive computational experience is reported.

INFORMS site uses cookies to store information on your computer. Some are essential to make our site work; Others help us improve the user experience. By using this site, you consent to the placement of these cookies. Please read our Privacy Statement to learn more.